Issue number one - the question of which side of Battery Lane to place a cycle track on - has now been answered by the County Department of Transportation, which has formally recommended it go on the south side of the street. Now MCDOT wants Aldon to resubmit the preliminary plan so that it can review all of the implications of placing it on the south side.
A second issue is stormwater exiting into the stormwater management pond by NIH. Regelin says the County has asked for an additional flood plain study for the relevant stormwater outlet there. This will require additional engineering study by Aldon, and further review by the County.
For these reasons, Aldon is asking to postpone the end of the preliminary plan review period to April 30, 2020. Planning staff is recommending approval of the extension. The extension request will be taken up by the Planning Board at its January 30, 2020 meeting.