Robert Dyer @ Bethesda Row here with the answers.
WHAT'S BEEN DONE
- Stormwater management construction along the site's border with the Capital Crescent Trail
- WSSC water line installed
- 70' long traffic signal arm is in place and wired on Woodmont Avenue. Now Pepco must connect it to electricity. It will be activated by September 1
- Pile driving on south side of former Lot 31 (delightful for adjacent residents, I'm sure)
- Restoration of Bethesda Avenue (Barnes and Noble) crosswalk is underway, and will be complete by August 8
WHAT'S NEXT
- Seeding and mulching work to begin Wednesday, August 1, and will last for 2 weeks. The developer advises CCT users to use caution
- Final WSSC water connections to be made by August 15
- Reconnection of Weiner Memorial water fountain
- Installation of overhead protection for CCT will occur between August 1-20
- Pile driving on western area of site, starting next week
Patience is a virtue at this time. Just remember, a 900 space garage will be part of the completed Darcy/Flats development.