Sunday, May 05, 2013

TOWER CRANE RISING AT FORMER MCDONALD'S CONSTRUCTION SITE IN BETHESDA (PHOTOS)

Here's an aerial view of the tower crane under assembly, at the Carr construction site at Montgomery Avenue and Pearl Street.

Formerly the longtime home of a McDonald's restaurant, it will eventually be a Class A office building.

Saturday, April 06, 2013

EXCLUSIVE VIDEO OF BLASTING AT 4500 EAST-WEST HIGHWAY IN BETHESDA YESTERDAY

Check out this video to see the actual detonation of explosive charges yesterday, at the 4500 East-West Highway construction site, from high above the site. Thanks to a very helpful reader for forwarding this. Blasting will resume Monday morning after 10:30 AM.

Friday, April 05, 2013

BLASTING TODAY AT 4500 EAST-WEST HIGHWAY CONSTRUCTION SITE IN DOWNTOWN BETHESDA

BAROOOOOM!

Contractors will be blasting today at the 4500 East-West Highway construction site, former home of the Bethesda McDonald's.

Detonations will occur between 10:30 AM and 2:30 PM.

If you are within 300 feet of the site, you can expect to hear an underground roar, and feel vibrations. (In my experience, it can be heard further than that!).  There will be an audible alert prior to blasting, a second alert just before detonation, and an all-clear signal after detonation. You know the drill.

Blasting is expected to resume again on Monday, same Blast time, same Blast channel. This will likely go on all next week.

What's going on, is that excavators struck an area of solid rock at the southern end of the site when digging. This is not unusual, given the geological makeup of the ground under Bethesda, or Montgomery County, in general. Blasting is now necessary to complete excavation.

Tuesday, March 05, 2013

BLASTING REQUIRED AT 4500 EAST-WEST HIGHWAY SITE, W LANE OF PEARL ST. TO CLOSE MARCH 12

The office building project at the former Bethesda McDonald's site (4500 East-West Highway) is about to get complicated.

If you work in one of the many office buildings nearby, or live in the Topaz House or Riviera and are at home during daytime hours, it's also going to get loud.

Workers excavating at the south end of the site have struck a layer of solid rock. An engineering study has clarified that blasting is necessary to continue excavation.

Blasting will begin in the coming weeks. If you live around Bethesda Row, you know the drill.

If not, here is the signal code explosive technicians will use during blasting at this site:

° Long horn blast warning, 5 minutes before detonation

° 3 short horn signal immediately before detonation

° "All Clear" long horn blast after explosion

Isn't that going to be fun?

The other big news, is that the western lane of Pearl Street will close "on or around" Tuesday, March 12, 2013.  Pearl Street, as I reported a few weeks ago, will become a southbound-only, one-way street for the duration of the building construction.

That western lane of Pearl will be sealed off with jersey barriers. And driver information signage will be placed along East-West Highway and Montgomery Avenue.

Support pile installation is now complete, and excavation will continue concurrent with blasting operations.

Friday, February 08, 2013

PEARL ST. TO BE ONE WAY DURING CONSTRUCTION AT FORMER BETHESDA MCDONALD'S SITE AT 4500 EAST-WEST HIGHWAY (PHOTO)

Pearl Street, between East-West Highway and Montgomery Avenue  in downtown Bethesda, will become a one-way street during construction of a Class A office building at the former McDonald's location.

According to the developer of 4500 East-West Highway, the southbound lane of Pearl Street will be closed indefinitely "on or about" February 18, 2013.

For the duration of the building construction, Pearl Street will be a one-way, southbound-only street. Drivers will be unable to turn left onto Pearl from Montgomery Avenue.

Reader Diarmaid McGleenan submitted this aerial-view photo of the former East-West Highway McDonald's site.  The restaurant was demolished a while ago.  At the top of the lot is the auger that just finished drilling for the installation of the steel I-beams you see around the perimeter of the growing hole.

The excavation machine is already filling dump trucks, and eventually a crane will arrive onsite.